Reconstruction of Kaiserlei traffic circle - Offenbach, Germany - 2021-2022
Project Management, Contract and Claim Management
The reconstruction at the Kaiserlei traffic circle means the end for what was once Europe’s largest traffic circle, which will be replaced by intersections, and is the start for the further development of the entire area. The reconstruction of the Kaiserlei traffic circle will separate the various traffic flows in the future: development traffic in the neighbourhood, traffic between Frankfurt and Offenbach, and feeder traffic to and from the A661 freeway. Subsequently, the City of Offenbach will have additional land to expand the commercial location.
- Total project costs: ± 60’ million EUR
Client
City of Offenbach, GermanyChallenges
Taking on an ongoing project as an external consultant requires the highest level of experience and commitment within a complex environment with many project participants and interests. Consistent project management and binding communication generates significant benefit for the customer and saves costs.
My role/position in the project
Project Management utility construction, responsible for:
- Project team support and impulse
- Implementation of supplementary claim processes
- Increase of binding communication to all project participants
- Project, Contract and Claims Management until acceptance and commissioning
Time duration project work
2021-2022